Campus Sustainability - 10 Year Plan


Water


Short-Term Goals (enacted since June 2007 or to be completed by end of 2009)
Intermediate Goals (1-5 years)
Goal W1 • Renovate restrooms in the Leon M. Goldstein Performing Arts Center to conserve water - Completed
Timeline 2009 - 2010
Actions to be taken • Install new low flow self-flush flush-o-meters in ladies and men's rooms in Performing Arts Center restrooms
• Installation of occupancy sensors
• Installation of touch-less, low flow faucets in restrooms.
 
Long-Term Goals (5-10 years)
Goal W2 Develop Immediate Response Program to Reported Water Leaks and as a result update College Facilities to Enhance KCC's Water Savings - IN PROGRESS
Goal Summary Objective
Prevent water and unnecessary water consumption by fixing existing leaks and establishing a program to maintain plumbing fixtures throughout campus.
Metrics for Success -
Reduce water consumption and lower utility bills by immediately responding to calls rather than processing through normal work orders
Timeline 2007 - 2017
Actions to be taken • Complaint received by Buildings & Grounds Office
• Call is dispatched to Plumbers
• Work is immediately assigned
• Plumber creates and completes work ticket once job is finished.
 
Goal W3 • Renovate T 2-& T-4-Building Bathrooms and T-4 laboratory to conserve water
Timeline 2010 - 2011
Actions to be taken • Install new low flow self-flush flush-o-meters in ladies and men's rooms in T-2 and T-4 Buildings.
• Install touch-less, low flow faucets
• Installation of occupancy sensors
• Installation of touch-less low flow faucets in T-4 Allied Health Laboratory..

kccFacebook KCCTwitter
Privacy Statement | GAINFUL EMPLOYMENT | Disclaimer | Text Only | Make This Website Talk

Kingsborough Community College
2001 Oriental Boulevard, Brooklyn, NY 11235-2398 | (718)-368-5000
Kingsborough is CUNY